— Project Summary

Queue ID
PJM-AG2-093
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Prince George, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPJMLBNL

100 MW hybrid in Prince George, VA · In queue since January 2021 · Proposed COD December 2024

100 MW

Capacity

1

Components

Solar

5y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 11m

Schedule

16 months past proposed COD

In Study38%
Queue EntryJan 26, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-01

Project Details

State

VA

County

Prince George

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Colonial Trail-Hopewell 230 kV

Data Source

LBNL

No news available for this project.