BetaActiveBatteryPJMLBNL
150 MW storage in Chesterfield, VA · In queue since January 2021 · Proposed COD April 2022
150 MW
Capacity
1
Components
Battery
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 3m
Schedule
48 months past proposed COD
In Study38%
Queue EntryJan 26, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-04-15
Project Details
State
VA
County
Chesterfield
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Midlothian 230 kV
Data Source
LBNL