BetaActiveSolarPJMLBNL
30 MW generation in Montgomery, KY · In queue since January 2021 · Proposed COD May 2024
30 MW
Capacity
1
Components
Solar
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 4m
Schedule
23 months past proposed COD
In Study38%
Queue EntryJan 21, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-05-01
Project Details
State
KY
County
Montgomery
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Mt. Sterling-Fogg Pike 69 kV
Data Source
LBNL
No news available for this project.