— Project Summary

Queue ID
PJM-AG2-074
Capacity
38 MW
Technology
Solar
Status
active
Location
Carbon, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

38 MW generation in Carbon, PA · In queue since January 2021 · Proposed COD December 2023

38 MW

Capacity

1

Components

Solar

5y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 11m

Schedule

27 months past proposed COD

In Study38%
Queue EntryJan 15, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

PA

County

Carbon

Region

PJM

Developer

Utility

PPL

Entity

PJM

Point of Interconnection

Meckesville Tap 69kV

Data Source

LBNL

No news available for this project.