Crooksville 69 kV — Project Summary

Queue ID
PJM-AG2-073 - moved to TC2
Capacity
53 MW
Technology
Solar
Status
active
Location
Madison, KY
Region
PJM
Developer
IA Status

Crooksville 69 kV

BetaActiveSolarPJMLive · PJM

53 MW generation in Madison, KY · In queue since March 2025

53 MW

Capacity

0

Components

1 year

In Queue

IA Status

Interconnection Timeline

Total Duration

1 year

Pre-Study0%
Queue EntryMar 4, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

KY

County

Madison

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Data Source

Live · PJM

No news available for this project.