BetaActiveGasPJMLBNL
700 MW generation in Spencer, IN · In queue since January 2021 · Proposed COD May 2026
700 MW
Capacity
1
Components
Gas
5y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 4m
In Study38%
Queue EntryJan 6, 2021
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-31
Project Details
State
IN
County
Spencer
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Rockport 765 kV
Data Source
LBNL
No news available for this project.