— Project Summary

Queue ID
PJM-AG2-068
Capacity
100 MW
Technology
Solar
Status
active
Location
Brunswick, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

100 MW generation in Brunswick, VA · In queue since December 2020 · Proposed COD December 2025

100 MW

Capacity

1

Components

Solar

5y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

5 years

Schedule

4 months past proposed COD

In Study38%
Queue EntryDec 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

VA

County

Brunswick

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Heritage-Wake 500 kV

Data Source

LBNL