BetaActiveWindPJMLBNL
147 MW generation in Grant, WV · In queue since December 2020 · Proposed COD August 2022
147 MW
Capacity
1
Components
Wind
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 8m
Schedule
44 months past proposed COD
In Study38%
Queue EntryDec 15, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-08-01
Project Details
State
WV
County
Grant
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Williams 138 kV
Data Source
LBNL
No news available for this project.