BetaActiveSolarPJMLBNL
17 MW generation in Morrow, OH · In queue since December 2020 · Proposed COD November 2022
17 MW
Capacity
1
Components
Solar
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
1y 11m
Schedule
40 months past proposed COD
In Study38%
Queue EntryDec 7, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-11-30
Project Details
State
OH
County
Morrow
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Cardington-Liberty 69 kV II
Data Source
LBNL
No news available for this project.