BetaActiveBatteryPJMLBNL
100 MW storage in Fulton, OH · In queue since December 2020 · Proposed COD September 2024
100 MW
Capacity
1
Components
Battery
5y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 9m
Schedule
18 months past proposed COD
In Study38%
Queue EntryDec 2, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-25
Project Details
State
OH
County
Fulton
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Fulton 138 kV
Data Source
LBNL
No news available for this project.