— Project Summary

Queue ID
PJM-AG2-053
Capacity
300 MW
Technology
Solar
Status
active
Location
Fulton, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

300 MW generation in Fulton, OH · In queue since December 2020 · Proposed COD September 2024

300 MW

Capacity

1

Components

Solar

5y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 9m

Schedule

18 months past proposed COD

In Study38%
Queue EntryDec 2, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-25

Project Details

State

OH

County

Fulton

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Fulton 138 kV

Data Source

LBNL

No news available for this project.