BetaActiveOtherPJMLBNL
20 MW generation in Arlington, VA · In queue since November 2020 · Proposed COD December 2020
20 MW
Capacity
1
Components
Other
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
1 month
Schedule
64 months past proposed COD
In Study38%
Queue EntryNov 20, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-12-31
Project Details
State
VA
County
Arlington
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Van Dorn 34.5 kV
Data Source
LBNL
No news available for this project.