BetaActiveSolarPJMLBNL
4.7 MW generation in Allegheny, PA · In queue since November 2020 · Proposed COD December 2021
4.7 MW
Capacity
1
Components
Solar
5y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 1m
Schedule
53 months past proposed COD
In Study38%
Queue EntryNov 13, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-01
Project Details
State
PA
County
Allegheny
Region
PJM
Developer
—
Utility
DL
Entity
PJM
Point of Interconnection
Findlay-Clinton 23 kV
Data Source
LBNL
No news available for this project.