300 MW generation in Noble, IN · In queue since October 2020 · Proposed COD June 2024
300 MW
Capacity
1
Components
Solar
5y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 8m
Schedule
22 months past proposed COD
In Study38%
Queue EntryOct 23, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
IN
County
Noble
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Forest G. Hipple-Collingwood 345 kV
Data Source
LBNL