— Project Summary

Queue ID
PJM-AG2-020
Capacity
7 MW
Technology
Battery
Status
active
Location
King George, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPJMLBNL

7 MW storage in King George, VA · In queue since October 2020 · Proposed COD December 2022

7 MW

Capacity

1

Components

Battery

5y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 2m

Schedule

39 months past proposed COD

In Study38%
Queue EntryOct 23, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-30

Project Details

State

VA

County

King George

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Arnolds Corner 34.5 kV

Data Source

LBNL

No news available for this project.