BetaActiveBatteryPJMLBNL
7 MW storage in King George, VA · In queue since October 2020 · Proposed COD December 2022
7 MW
Capacity
1
Components
Battery
5y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 2m
Schedule
39 months past proposed COD
In Study38%
Queue EntryOct 23, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-30
Project Details
State
VA
County
King George
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Arnolds Corner 34.5 kV
Data Source
LBNL
No news available for this project.