BetaActiveSolarPJMLBNL
19.8 MW generation in Ocean, NJ · In queue since October 2020 · Proposed COD December 2021
19.8 MW
Capacity
1
Components
Solar
5y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 2m
Schedule
52 months past proposed COD
In Study38%
Queue EntryOct 20, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-17
Project Details
State
NJ
County
Ocean
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Oyster Creek-Whitings 34.5 kV
Data Source
LBNL
No news available for this project.