BetaActiveBatteryPJMLBNL
100 MW storage in City Of Hampton, VA · In queue since October 2020 · Proposed COD January 2023
100 MW
Capacity
1
Components
Battery
5y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 3m
Schedule
39 months past proposed COD
In Study38%
Queue EntryOct 9, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-01-01
Project Details
State
VA
County
City Of Hampton
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Peninsula-Whealton 115 kV
Data Source
LBNL