20 MW generation in Erie, PA · In queue since October 2020 · Proposed COD March 2023
20 MW
Capacity
1
Components
Solar
5y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 5m
Schedule
36 months past proposed COD
In Study38%
Queue EntryOct 8, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-03-30
Project Details
State
PA
County
Erie
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Erie South-Warren 230 kV II
Data Source
LBNL