— Project Summary

Queue ID
PJM-AG2-005
Capacity
20 MW
Technology
Solar
Status
active
Location
Lancaster, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarPJMLBNL

20 MW generation in Lancaster, VA · In queue since October 2020 · Proposed COD December 2022

20 MW

Capacity

1

Components

Solar

5y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 2m

Schedule

39 months past proposed COD

In Study38%
Queue EntryOct 2, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

VA

County

Lancaster

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Garner-Lancaster 115 kV

Data Source

LBNL

No news available for this project.