Rainbow Trout — Project Summary

Queue ID
PJM-AG1-555
Capacity
120 MW
Technology
Solar+Battery
Status
active
Location
Tippecanoe, IN
Region
PJM
Developer
IA Status
IA Executed

Rainbow Trout

BetaActiveSolarBatteryPJMLBNL + Live

120 MW hybrid in Tippecanoe, IN · In queue since September 2020 · Proposed COD January 2029

120 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Executed

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

8y 4m

Construction75%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2029-01-31

Project Details

State

IN

County

Tippecanoe

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Dequine 345 kV

Data Source

LBNL + Live

No news available for this project.