— Project Summary

Queue ID
PJM-AG1-548
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Erie, PA
Region
PJM
Developer
IA Status
Feasibility Study

BetaActiveSolarBatteryPJMLBNL

150 MW hybrid in Erie, PA · In queue since September 2020 · Proposed COD October 2022

150 MW

Capacity

1

Components

Solar

5y 6m

In Queue

Feasibility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 1m

Schedule

41 months past proposed COD

Feasibility Study13%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-31

Project Details

State

PA

County

Erie

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Erie South-Union City 115 kV

Data Source

LBNL