BetaActiveSolarBatteryPJMLBNL
150 MW hybrid in Erie, PA · In queue since September 2020 · Proposed COD October 2022
150 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Feasibility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 1m
Schedule
41 months past proposed COD
Feasibility Study13%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-10-31
Project Details
State
PA
County
Erie
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Erie South-Union City 115 kV
Data Source
LBNL
No news available for this project.