Fields 2
BetaActiveSolarPJMLBNL + Live
13.5 MW generation in Greensville, VA · In queue since September 2020 · Proposed COD January 2028
13.5 MW
Capacity
1
Components
Solar
5y 6m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 4m
Impact Study25%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-01-31
Project Details
State
VA
County
Greensville
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Fields 34.5 kV
Data Source
LBNL + Live
No news available for this project.