BetaActiveSolarPJMLBNL
222 MW generation in Garrard, KY · In queue since September 2020 · Proposed COD June 2023
222 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Feasibility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 9m
Schedule
34 months past proposed COD
Feasibility Study13%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-06-01
Project Details
State
KY
County
Garrard
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
West Garrard 345 kV
Data Source
LBNL