Beechurt Natural Gas — Project Summary

Queue ID
PJM-AG1-517
Capacity
50 MW
Technology
Gas
Status
active
Location
Monongalia, WV
Region
PJM
Developer
IA Status
IA Executed

Beechurt Natural Gas

BetaActiveGasPJMLBNL + Live

50 MW generation in Monongalia, WV · In queue since September 2020 · Proposed COD January 2028

50 MW

Capacity

1

Components

Gas

5y 6m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 4m

Construction75%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2028-01-31

Project Details

State

WV

County

Monongalia

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Osage 138 kV

Data Source

LBNL + Live

No news available for this project.