Aurora Battery Storage — Project Summary

Queue ID
PJM-AG1-513
Capacity
10 MW
Technology
Battery
Status
suspended
Location
Will, IL
Region
PJM
Developer
IA Status
IA Executed

Aurora Battery Storage

BetaSuspendedBatteryPJMLBNL + Live

10 MW storage in Will, IL · In queue since October 2020 · Proposed COD June 2028

10 MW

Capacity

1

Components

Battery

5y 5m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 8m

Suspended75%
Queue EntryOct 1, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

IL

County

Will

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Aurora 138 kV

Data Source

LBNL + Live