West Lorain Power Plant 345 kV
BetaActiveGasPJMLBNL + Live
406.4 MW generation in Lorain, OH · In queue since September 2020 · Proposed COD June 2031
406.4 MW
Capacity
1
Components
Gas
5y 6m
In Queue
IA Executed
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
10y 9m
Construction75%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2031-06-01
Project Details
State
OH
County
Lorain
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Beaver 345 kV
Data Source
LBNL + Live