Esky Solar Project — Project Summary

Queue ID
PJM-AG1-499
Capacity
10 MW
Technology
Solar
Status
active
Location
Gloucester, NJ
Region
PJM
Developer
IA Status
System Impact Study

Esky Solar Project

BetaActiveSolarPJMLBNL + Live

10 MW generation in Gloucester, NJ · In queue since September 2020 · Proposed COD August 2026

10 MW

Capacity

1

Components

Solar

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 11m

Impact Study25%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-08-31

Project Details

State

NJ

County

Gloucester

Region

PJM

Developer

Utility

AEC

Entity

PJM

Point of Interconnection

Lambs 12.47 kV

Data Source

LBNL + Live

No news available for this project.