Esky Solar Project
BetaActiveSolarPJMLBNL + Live
10 MW generation in Gloucester, NJ · In queue since September 2020 · Proposed COD August 2026
10 MW
Capacity
1
Components
Solar
5y 6m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 11m
Impact Study25%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-08-31
Project Details
State
NJ
County
Gloucester
Region
PJM
Developer
—
Utility
AEC
Entity
PJM
Point of Interconnection
Lambs 12.47 kV
Data Source
LBNL + Live
No news available for this project.