Fourth Quarter
BetaActiveBatteryPJMLBNL
500 MW storage in Montgomery, MD · In queue since October 2020 · Proposed COD June 2024
500 MW
Capacity
1
Components
Battery
5y 5m
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 8m
Schedule
22 months past proposed COD
Impact Study25%
Queue EntryOct 1, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
MD
County
Montgomery
Region
PJM
Developer
—
Utility
PEPCO
Entity
PJM
Point of Interconnection
Dickerson 230 kV
Data Source
LBNL
No news available for this project.