54 MW generation in KY · In queue since September 2020 · Proposed COD October 2023
54 MW
Capacity
1
Components
Solar
5y 6m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 1m
Schedule
30 months past proposed COD
Impact Study25%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-10-02
Project Details
State
KY
County
—
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Up Church-Wayne County 69 kV
Data Source
LBNL