Turkey Solar
BetaActiveSolarPJMLBNL + Live
14.04 MW generation in Louisa, VA · In queue since September 2020 · Proposed COD August 2027
14.04 MW
Capacity
1
Components
Solar
5y 6m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 11m
Impact Study25%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-29
Project Details
State
VA
County
Louisa
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Gordonsville 34.5 kV
Data Source
LBNL + Live
No news available for this project.