Turkey Solar — Project Summary

Queue ID
PJM-AG1-469
Capacity
14.04 MW
Technology
Solar
Status
active
Location
Louisa, VA
Region
PJM
Developer
IA Status
System Impact Study

Turkey Solar

BetaActiveSolarPJMLBNL + Live

14.04 MW generation in Louisa, VA · In queue since September 2020 · Proposed COD August 2027

14.04 MW

Capacity

1

Components

Solar

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

6y 11m

Impact Study25%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-08-29

Project Details

State

VA

County

Louisa

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Gordonsville 34.5 kV

Data Source

LBNL + Live

No news available for this project.