BetaActiveSolarPJMLBNL
255 MW generation in Whiteside, IL · In queue since October 2020 · Proposed COD October 2023
255 MW
Capacity
1
Components
Solar
5y 5m
In Queue
Feasibility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3 years
Schedule
30 months past proposed COD
Feasibility Study13%
Queue EntryOct 1, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-10-01
Project Details
State
IL
County
Whiteside
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Cordova 345 kV
Data Source
LBNL
No news available for this project.