25 MW storage in Dorchester, MD · In queue since September 2020 · Proposed COD December 2022
25 MW
Capacity
1
Components
Battery
5y 6m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 3m
Schedule
39 months past proposed COD
Impact Study25%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
MD
County
Dorchester
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Airey-Vienna 69 kV II
Data Source
LBNL
No news available for this project.