— Project Summary

Queue ID
PJM-AG1-433
Capacity
100 MW
Technology
Wind
Status
active
Location
Blackford, IN
Region
PJM
Developer
IA Status
Feasibility Study

BetaActiveWindPJMLBNL

100 MW generation in Blackford, IN · In queue since September 2020 · Proposed COD December 2023

100 MW

Capacity

1

Components

Wind

5y 6m

In Queue

Feasibility Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 3m

Schedule

27 months past proposed COD

Feasibility Study13%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

IN

County

Blackford

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Keystone-DeSoto 345 kV

Data Source

LBNL

No news available for this project.