— Project Summary

Queue ID
PJM-AG1-414
Capacity
75 MW
Technology
Solar+Battery
Status
active
Location
Grant, IN
Region
PJM
Developer
IA Status
Facility Study

BetaActiveSolarBatteryPJMLBNL + Live

75 MW hybrid in Grant, IN · In queue since September 2020 · Proposed COD April 2028

75 MW

Capacity

1

Components

Solar

5y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 7m

Facilities Study50%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-20

Project Details

State

IN

County

Grant

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Mississinewa 138 kV

Data Source

LBNL + Live

No news available for this project.