BetaActiveSolarBatteryPJMLBNL + Live
75 MW hybrid in Grant, IN · In queue since September 2020 · Proposed COD April 2028
75 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 7m
Facilities Study50%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-20
Project Details
State
IN
County
Grant
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Mississinewa 138 kV
Data Source
LBNL + Live
No news available for this project.