BetaActiveBatteryPJMLBNL
22 MW storage in Mclean, KY · In queue since September 2020 · Proposed COD September 2024
22 MW
Capacity
1
Components
Battery
5y 6m
In Queue
System Impact Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4 years
Schedule
18 months past proposed COD
Impact Study25%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-25
Project Details
State
KY
County
Mclean
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Walnut Grove-Asahi 69 kV
Data Source
LBNL
No news available for this project.