— Project Summary

Queue ID
PJM-AG1-378
Capacity
20 MW
Technology
Solar
Status
active
Location
Centre, PA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

20 MW generation in Centre, PA · In queue since September 2020 · Proposed COD August 2023

20 MW

Capacity

1

Components

Solar

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 11m

Schedule

32 months past proposed COD

Impact Study25%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-08-15

Project Details

State

PA

County

Centre

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Philipsburg 115 kV

Data Source

LBNL

No news available for this project.