Furnace View Farms — Project Summary

Queue ID
PJM-AG1-362
Capacity
5 MW
Technology
Solar
Status
suspended
Location
Berks, PA
Region
PJM
Developer
IA Status
System Impact Study

Furnace View Farms

BetaSuspendedSolarPJMLBNL + Live

5 MW generation in Berks, PA · In queue since September 2020 · Proposed COD December 2023

5 MW

Capacity

1

Components

Solar

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 3m

Suspended25%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-29

Project Details

State

PA

County

Berks

Region

PJM

Developer

Utility

PPL

Entity

PJM

Point of Interconnection

Wernersville 12.47 kV