Carnation — Project Summary

Queue ID
PJM-AG1-351
Capacity
58 MW
Technology
Solar
Status
active
Location
Fairfield, OH
Region
PJM
Developer
IA Status
IA Executed

Carnation

BetaActiveSolarPJMLBNL + Live

58 MW generation in Fairfield, OH · In queue since September 2020 · Proposed COD March 2028

58 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 6m

Construction75%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-03-31

Project Details

State

OH

County

Fairfield

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Harrison-Good Hope 138 kV

Data Source

LBNL + Live