New Jay PV & BESS
BetaActiveSolarBatteryPJMLBNL + Live
39 MW hybrid in Jay, IN · In queue since September 2020 · Proposed COD September 2028
39 MW
Capacity
1
Components
Solar
5y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8 years
Construction75%
Queue EntrySep 30, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-09-17
Project Details
State
IN
County
Jay
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Jay-Desoto 138 kV
Data Source
LBNL + Live
News & Articles (1)Beta