— Project Summary

Queue ID
PJM-AG1-323
Capacity
40 MW
Technology
Solar+Battery
Status
active
Location
Logan, OH
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPJMLBNL

40 MW hybrid in Logan, OH · In queue since September 2020 · Proposed COD September 2023

40 MW

Capacity

1

Components

Solar

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3 years

Schedule

31 months past proposed COD

Impact Study25%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-09-01

Project Details

State

OH

County

Logan

Region

PJM

Developer

Utility

Dayton

Entity

PJM

Point of Interconnection

Blue Jacket 138 kV

Data Source

LBNL

No news available for this project.