— Project Summary

Queue ID
PJM-AG1-302
Capacity
300 MW
Technology
Solar
Status
active
Location
Pulaski, IN
Region
PJM
Developer
IA Status
Facility Study

BetaActiveSolarPJMLBNL + Live

300 MW generation in Pulaski, IN · In queue since September 2020 · Proposed COD January 2028

300 MW

Capacity

1

Components

Solar

5y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 4m

Facilities Study50%
Queue EntrySep 29, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-15

Project Details

State

IN

County

Pulaski

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Olive-Reynolds #1 345 kV

Data Source

LBNL + Live