BetaActiveSolarPJMLBNL
450 MW generation in Fountain, IN · In queue since September 2020 · Proposed COD June 2024
450 MW
Capacity
1
Components
Solar
5y 6m
In Queue
Feasibility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 9m
Schedule
22 months past proposed COD
Feasibility Study13%
Queue EntrySep 24, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-06-01
Project Details
State
IN
County
Fountain
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Eugene-Dequine 345 kV
Data Source
LBNL
No news available for this project.