Monmouth Solar 1 — Project Summary

Queue ID
PJM-AG1-223
Capacity
15.4 MW
Technology
Solar
Status
active
Location
Monmouth, NJ
Region
PJM
Developer
IA Status
IA Executed

Monmouth Solar 1

BetaActiveSolarPJMLBNL + Live

15.4 MW generation in Monmouth, NJ · In queue since September 2020 · Proposed COD December 2026

15.4 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6y 3m

Construction75%
Queue EntrySep 23, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

NJ

County

Monmouth

Region

PJM

Developer

Utility

JCPL

Entity

PJM

Point of Interconnection

Larrabee-Allaire 34.5 kV

Data Source

LBNL + Live

No news available for this project.