Lacey Sand Solar
BetaActiveSolarPJMLBNL + Live
19.8 MW generation in Ocean, NJ · In queue since September 2020 · Proposed COD June 2028
19.8 MW
Capacity
1
Components
Solar
5y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 9m
Construction75%
Queue EntrySep 17, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
NJ
County
Ocean
Region
PJM
Developer
—
Utility
JCPL
Entity
PJM
Point of Interconnection
Manitou-Oyster Creek 34.5 kV
Data Source
LBNL + Live
No news available for this project.