BetaActiveSolarPJMLBNL
15 MW generation in Nottoway, VA · In queue since September 2020 · Proposed COD October 2021
15 MW
Capacity
1
Components
Solar
5y 6m
In Queue
System Impact Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 1m
Schedule
54 months past proposed COD
Impact Study25%
Queue EntrySep 16, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-10-15
Project Details
State
VA
County
Nottoway
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Lone Pine 115 kV
Data Source
LBNL
No news available for this project.