— Project Summary

Queue ID
PJM-AG1-167
Capacity
15 MW
Technology
Solar
Status
active
Location
Nottoway, VA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

15 MW generation in Nottoway, VA · In queue since September 2020 · Proposed COD October 2021

15 MW

Capacity

1

Components

Solar

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

1y 1m

Schedule

54 months past proposed COD

Impact Study25%
Queue EntrySep 16, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-10-15

Project Details

State

VA

County

Nottoway

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Lone Pine 115 kV

Data Source

LBNL

No news available for this project.