— Project Summary

Queue ID
PJM-AG1-153
Capacity
75 MW
Technology
Battery
Status
active
Location
Brunswick, VA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveBatteryPJMLBNL

75 MW storage in Brunswick, VA · In queue since September 2020 · Proposed COD December 2023

75 MW

Capacity

1

Components

Battery

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 3m

Schedule

28 months past proposed COD

Impact Study25%
Queue EntrySep 10, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-01

Project Details

State

VA

County

Brunswick

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Heritage 500 kV

Data Source

LBNL

No news available for this project.