— Project Summary

Queue ID
PJM-AG1-152
Capacity
100 MW
Technology
Battery
Status
active
Location
Fauquier, VA
Region
PJM
Developer
IA Status
Facility Study

BetaActiveBatteryPJMLBNL + Live

100 MW storage in Fauquier, VA · In queue since September 2020 · Proposed COD September 2029

100 MW

Capacity

1

Components

Battery

5y 6m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

9 years

Facilities Study50%
Queue EntrySep 10, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-01

Project Details

State

VA

County

Fauquier

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Remington CT 230 kV

Data Source

LBNL + Live

No news available for this project.