— Project Summary

Queue ID
PJM-AG1-135
Capacity
60 MW
Technology
Solar
Status
active
Location
Richmond, VA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

60 MW generation in Richmond, VA · In queue since September 2020 · Proposed COD December 2024

60 MW

Capacity

1

Components

Solar

5y 6m

In Queue

System Impact Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

4y 3m

Schedule

16 months past proposed COD

Impact Study25%
Queue EntrySep 3, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-01

Project Details

State

VA

County

Richmond

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Garner-Lancaster 115 kV

Data Source

LBNL