Oak Run Solar Project — Project Summary

Queue ID
PJM-AG1-125
Capacity
400 MW
Technology
Solar
Status
active
Location
Madison, OH
Region
PJM
Developer
IA Status
IA Executed

Oak Run Solar Project

BetaActiveSolarPJMLBNL + Live

400 MW generation in Madison, OH · In queue since August 2020 · Proposed COD December 2030

400 MW

Capacity

1

Components

Solar

5y 7m

In Queue

IA Executed

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

10y 4m

Construction75%
Queue EntryAug 31, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2030-12-31

Project Details

State

OH

County

Madison

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Marysville-Flatlick 765 kV

Data Source

LBNL + Live

No news available for this project.