Oak Run Solar Project
BetaActiveSolarPJMLBNL + Live
400 MW generation in Madison, OH · In queue since August 2020 · Proposed COD December 2030
400 MW
Capacity
1
Components
Solar
5y 7m
In Queue
IA Executed
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
10y 4m
Construction75%
Queue EntryAug 31, 2020
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2030-12-31
Project Details
State
OH
County
Madison
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Marysville-Flatlick 765 kV
Data Source
LBNL + Live
No news available for this project.