300 MW generation in Dekalb, IL · In queue since August 2020 · Proposed COD December 2023
300 MW
Capacity
1
Components
Solar
5y 7m
In Queue
Feasibility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 4m
Schedule
27 months past proposed COD
Feasibility Study13%
Queue EntryAug 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-29
Project Details
State
IL
County
Dekalb
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Sugar Grove-Waterman 138kV
Data Source
LBNL